Construction.
In this section I'm going to run through the building of those sections
mentioned on the previous page. Although the specifics of certain systems
may require you to alter these plans, the general methods involved will stay
the same. I will start off with the main plumbing i.e. overflows and
returns, and then progress onto the closed loops.
As a pre curser, here is a quick reminder of the full plumbing set up.
There have been certain alterations to this design over time, with the
addition of a fifth closed loop and the re-placement of the two closed loop
pumps that were originally going to sit on the top braces at the back
corners. I have now shifted all pumps down into the cabinet for neatness and
simplicity. At this moment in time though I'm pondering over replacing 4 of
the Aquabee 3000's with two Ocean Runner 6500's. This wont make any major
difference to the overall plumbing layout. All it will involve is the teeing
of two of the closed loop returns into each outlet of the bigger Ocean
Runners, and likewise with the input end. In this case I may review the 5
central take offs, and swap them for two 32mm take offs instead.

The pumps shown above make up the various links in the system comprising
of. 'A' skimmer feed pump taken from the first sump compartment. 'B' the 5
closed loop pumps with the intakes running down from the top centre of the
tank via a strainer box. These then run out from the pumps and back up to
the various outlets of the 5 loops. 'C' These are the two return pumps for
the sump which can be switched independently depending on the turnover
required. Obviously there will be subtle differences if I do go down the
twin OR6500 route, but as I said before, these will be minimal simply
involving teeing a few of the pipes together to form single connectors to
the pumps. The brown pipes represent the overflow pipes coming from the
weirs as shown in my DIY section via a 90deg bulkhead fitting, one of which
is teed off to the raised DSB..
Overflows.
In an effort to ensure adequate flow of water back to the sump it was
important that I used a pipe and bulkhead fitting with a diameter that would
easily cope with the amount of water coming back up from the pumps. I
decided prior to ordering the tank that I wanted two overflows for safety
reasons i.e. blockages, and to evenly draw water/waste from both ends of the
tank. So the tank was ordered with two 55mm holes which
would give me scope for various sized bulkhead fittings. In the end I opted
for 40mm 'Marley' push fit waste pipe, coupled up to a bulkhead fitting that
would take water from the overflow weirs and strait down to the sump. I had
to take certain factors into consideration, such as 'Teeing off' the DSB
feed from one of them. So in the end I decided that the pipe on the right
hand side of the tank (when viewed from the rear) would be the split
overflow/DSB feed. Whilst the LHS pipe would run strait to the sump and
compartment 1 where the skimmer take off is situated. Both these sections
were constructed using 'push fit' piping, so it was important to support any horizontal sections 'I.e. those
that run along the top of the sump' to prevent the possibility of the joints
being pushed apart with the force of water hurtling down from the tank and
then hitting the first bend.
In the photo's below you can see how, by using several 45deg bends I have
brought the pipe down, into the sump bay, and then along the side of the sump
tank. From this a Tee junction is inserted onto which a further 90deg
bend is added to divert flow down into the DSB. On the end of this pipe is a
strait link with an end cap inserted to prevent masses of bubbles
making a pest of themselves. Holes are drilled into the strait pipe above
the coupling to allow water and detritus to flow 'across' the DSB rather
than strait down onto the sand surface which would cause disturbance of the
sand layers. This type of drilled end, also means that food or
detritus is evenly distributed over the entire bed, and not just one
section. The ends that sit in the first sump compartment spend their time submerged.
This is to reduce noise and bubbles when water flows out. (pic 2) . To increase or
decrease the amount of flow that enters the DSB, the tee junction is simply
tilted on its seal, (pic 1 'A') 'down' = more flow to the sand bed and less to the sump,
or 'up' = less flow to the sand bed, and more to the sump. Any
surplus water flows past the tee, and strait out the end into sump
compartment 1. By tilting the Tee strait up, it lifts the DSB feed pipe out
and up, which cuts off flow to the DSB area completely, should I need to do
any work on the bed itself. Or to salvage/protect either the tank or DSB in
the event of a catastrophe, whilst still being able to utilise the rest of
the sump.
1.

2.

Closed Loops.
Here are some simple schematics of
the layout for each closed loop.



The following pictures show the various closed loops and
how they were laid out inside the tank. I felt that this layout gave the best
look i.e. neatness, whilst at the same time keeping pipe lengths to
respectable levels in the interests of friction loss. Once the tank was
running, the only visible piping was the two corner outlets and the
bottom of the outflow box. Just the nozzles were visible on the front
sand bed loop. If I was to do it
again I would be very tempted to drill several holes in the top of the back
panel and pass each pipe through via bulkhead fitting rather than over the
top. although there is the
added risk of stressing the panel when dealing with multiple holes, so its a
personal choice really.
Just click on the smaller pic for a full view.
Closed loop Outlets/intakes
This shows the front closed loop that comes down from the LH back corner, along the side under the sand bed, and then along the front, with the three outputs along its length that protrude from the surface of the sand bed. As mentiond before, this is to recirculate water upwards from the sand bed towards the rockwork.
This closed loop runs from the top back LH corner, along the top back brace and then out to the reef column. This runs down the middle of this column using a spary bar desighn.
This loop runs down from the top RH back corner, and then along the side under the sand bed. It then enters under the LR island and forces water up through the LR via a spraybar desighn.
This shows the layout of how each loop goes over the back panel. It also shows Loop 4, which is the LH rear corner outlet This has three adjustable nozzles. and is duplicated at the other end of the tank for Loop 5.
All five takeoffs are grouped together, in a single location at the top centre of the tank. The slotted bottom on the box desperses the force of the suction from the pumps to prevent anything being sucked up an intake. Approximately 15,000 lph will be going through this section so despersing this suction was very important.
This shows how each closed loop runs over the back of the tank.
This shows the front closed loop that comes down from the LH back corner, along the side under the sand bed, and then along the front, with the three outputs along its length that protrude from the surface of the sand bed. As mentiond before, this is to recirculate water upwards from the sand bed towards the rockwork.
Return Pump feed.
For the returns, certain
aspects had to be kept in mind. Specifically what happens if and when the
pumps go off. In systems that utilise drilled rear panels for overflows and
returns, this should always be accounted for. By and large, an overflow weir
does not concern us, as the top edge of the weir itself creates and sets the
water level in the tank. The problems arise when we are feeding or taking
water from anywhere below the surface be it from over the back panel or
through it. Since the level of the return nozzles is below that of
the water level in the tank, there would have been the danger that when the
pumps go off, a large amount of water would back siphon into to sump from
the tank itself, in this case about 35gallons (or the top 6" of water that
sits above these nozzles in the tank) which is way over the spare
space left in the sump when at its normal running level, so it would have
meant a flood. To get round this, a simple anti-siphon setup is installed
utilising an up-turned 'U' bend.
As
can be seen from the picture. Water flows from the return pump up to the
bend assembly and then back down to the outlet nozzle which is situated
through the drilled hole in the tanks back panel via a bulkhead fitting. At
the top of this bend I have drilled a small hole into which a small bore
solid pipe (5mm external/3mm internal) is sealed. this pipe runs strait out
from the top of this section, and over the top lip of the tank, ending with
a bend that runs down to sit just clear of the water surface as set by the
overflow weirs. When the return pumps are running water is pushed up the
main pipe and out through the nozzle, however a small amount of water is
also forced along the small pipe to exit into the tank as well.
In the event of the pumps being switched off, or the
power failing. Air is drawn into the small pipe by the suction/siphon effect
of water falling back down the main pipe to the sump. this fills the top of
the bend assembly with air and the siphon is broken. The only water to make
it back to the sump is the volume of water that was originally held in the
pipe. When the pumps come back on, the whole assembly fills again as before.
Although there is some extra head pressure created by
forcing the water up higher than would normally be required (i.e.
about 4" above the water surface in the main tank). this is counteracted by
the drop back down to the nozzle. In effect the only additional work the
pump has to do, is moving water round the two 90deg bends.
The following photos show the assembly prior to, and after
fitting to the tank.
(Note:
Many thanks to Ed Miller AKA 'Dragon' on at Ultimatereef.com for this idea,,
cheers Ed)
Construction of 'Marley' Solvent weld
21.5mm piping.
Since every set up will vary slightly I have refrained
from going into too much detail on each section i.e. lengths etc.. But here
are a few hints and tips I've picked up on the way which should help you if
you wish to have a go at your own piping.
1. Make sure that the cut
ends on each pipe are square. There are proper pipe cutters on the market
however a saw will suffice if your careful, and take your time. After each
piece has been cut, the ends will need de-burring and smoothing. Running a
Stanley knife round the inside of the end will do this quite nicely.
2. Make sure that the
ends of the piping are clean and grease free prior to bonding to avoid
leaks, or weak joints that will blow under pressure. Likewise blow through
each pipe to get rid of any 'swarf' that has collected on the inside from
the cutting process.
3. The glue used in
solvent weld pipe, is very fast acting i.e. 5-10 sec until the joint becomes
unmoveable. Baring this in mind, I would strongly advise that you make each
section/loop, up fully in a loose fit fashion prior to welding. This will
save you allot of money 'and joints' later on, as once a joint has been
bonded it is impossible to break.
4. Once you are happy
that everything fits together ok and lines up nice and neat you can start to
weld up each piece in turn. Start at one end and work your way along in
order.
5. When bonding sections
that have multiple couplings etc or a piece of pipe with a 90 or 45deg bend
at each end, my best advise would be to lay them on a flat/work surface as
you glue them together this will ensure that joints are square to each other, and run
true.
6. When applying the
glue, smear a small amount round the 'inside' of the coupling face, rather
than the end of the pipe that will slot inside. If glue is applied to the
pipe end, it will be pushed back as the pipe is pushed into the coupling
creating a weak bond. Smearing glue round the internal face of the coupling
and then spinning the inserted pipe through 90deg will ensure an even
coverage of glue round the joint faces and give a better seal/bond.
7. Over the course of
time, it will become essential to clean your plumbing out at least once
every two years if not every year due to the microbial / algal build up that
occurs. Doing this is quite simple. Remove the section of tubing you wish to
work on. Then pass a length of string or fishing line down it with a small
weight attached that will fall along the pipe. At the other end of this,
attach half a plate scourer (non toxic type) and simply pull through to the
other end. 'You may have to do this a couple of times'. Running hot water
down the pipe first will help loosen any stubborn build-up, although
calcareous build-up can only be removed by filling the section up with a
mild vinegar solution for a few hours and then flushing through
thoroughly.
Important note.
Once your plumbing is completed and your tank
is filled. Don't forget to bleed each loop through, prior to turning on your
pumps. Fitting a bleed nozzle at a high point in each loop will make this
easier. (Starting pumps up dry, may severely damage them).
Also, never forget to fit shut off taps on both sides
of a closed loop pump, and externally mounted return pumps. this is the only way to
shut them off for removal should they need maintanance.
Hopefully, this section has given you some ideas or at least a head start if
you want to do your own plumbing.
Have fun........Si.